|
Construction Consortium Publishes Update On
Olkiluoto-3
20 Oct (NucNet): The Areva-Siemens consortium
constructing the Olkiluoto-3 European
pressurised water reactor (EPR) unit in Finland
said that confronted with construction delays,
it succeeded in convincing utility Teollisuuden
Voima Oyj (TVO) that a number of measures were
required to �accelerate and improve� the
programme.
Areva said in a statement that TVO will be �chiefly
responsible� for implementing these measures.
The statement said that the Areva-Siemens
consortium signed a turnkey contract with TVO
under which the customer committed to validating
documents sent by the consortium to the Finnish
Radiation and Nuclear Safety Authority (STUK)
within two months, but in fact TVO is taking an
average of nine months to do so.
The consortium has also started arbitration
proceedings for a number of other contractual
aspects, the statement said.
The Areva-Siemens consortium will update the
construction schedule by the end of the year,
depending on the progress made.
The statement said the manufacture of the
primary components, the reactor vessel and the
first steam generator has been completed.
Forging for the reactor coolant pipes has been
validated, and Areva representatives are on hand
in the plants of suppliers of more than 10,000
components to ensure that they are delivered as
quickly as possible.
Areva-Siemens also pointed out that STUK has
expressed its satisfaction with the consortium�s
services concerning nuclear and occupational
safety. These two aspects continue to be the
consortium�s top priority, the statement said.
TVO announced last week that civil construction
works at Olkiluoto-3 will take several months
longer than expected, resulting in a possible
delay to the startup of the unit until 2012.
But the company denied media reports that it has
been negotiating to share possible losses
stemming from the delay with Areva-Siemens.
This is not the first time the schedule for
Olkiluoto-3 has changed. In December 2006,
Areva-Siemens said commissioning had been pushed
back to the end of 2010 or beginning of 2011, a
delay of up to one year from previous estimates,
because construction work had been slower than
planned. In December 2007 the schedule was
revised again with a commissioning date of
summer 2011.
>>Related reports in the NucNet database (available
to subscribers)
Finnish Utility �Disappointed� Over New Setback
For Olkiluoto-3 (News No. 186, 10 August 2007
Finland�s Olkiluoto-3 Estimated To Start
Operation In Summer 2011 (News No. 264, 28
December 2008)
Process Starts To Find Next IAEA Chief (World
Nuclear Review No. 40, 17 October 2008)
The NucNet database currently contains around
12,000 reports published since 1991. To
subscribe or ask for any further information
email
info@worldnuclear.org
|